ANNA DRIVE UPDATE
3/20/2024
Current status from the Engineering Company:
The contractor for the Anna Drive Project is going to do "pre-cast" instead of "port in place". This is a better and faster process. The shop drawings are due to the Engineer this week for approval and then the "pre-cast" can be poured. Water lines will be moved beginning April 1st and other pre-work will be done prior to the cast coming in. If by chance the cast of the culvert is done sooner, it will be delivered sooner. It will be delivered as one huge piece instead of having to do rebar and additional work at the site.